The launch of the 330-metre-long, 2,000-tonne steel bridge structure from the eastern bank of the Ölfusá river to the western bank went very smoothly. This article includes a video explaining the operation.
Powerful hydraulic jacks were used to pull the bridge deck forward over specially designed launching bearings. The steel structure rested on pads that slid over smooth steel plates to prevent damage to the surfaces of the steel beams.
The jacks advanced the bridge deck approximately half a metre at a time. Under optimal conditions, it was expected to move at around ten metres per hour, but the entire operation took considerably less time than anticipated.
A large temporary mast was installed on the bridge deck to support it during the launch across the river. Steel cables extending from the mast supported the leading end of the deck throughout the operation.

Hér sést vel

Til að styðja við brúargólfið á meðan það var dregið yfir ána var komið fyrir stóru bráðabirgðamastri ofan á því.

Brúargrindin er 330 m löng og vegur 2000 tonn.